The correct answer is C: Risk register. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
Which of the following documents is described in the statement below? "It is developed along with all processes of the risk management. It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning."
Options
- ARisk management plan
- BProject charter
- CRisk register
- DQuality management plan
Topics
#Risk Register#Risk Management Documentation#Qualitative Risk Analysis#Quantitative Risk Analysis