nerdexam
PMIPMI

PMI-RMP · Question #40

PMI-RMP Question #40: Real Exam Question with Answer & Explanation

The correct answer is C: These risks can be added to a low priority risk watch list.. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won't affect your project much if they happen. What should you do with these identified risk events?

Options

  • AAll risks must have a valid, documented risk response.
  • BThese risks can be accepted.
  • CThese risks can be added to a low priority risk watch list.
  • DThese risks can be dismissed.

Topics

#Risk identification#Risk response strategies#Risk watchlist#Low priority risks

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions