PMIPMI
PMI-RMP · Question #40
PMI-RMP Question #40: Real Exam Question with Answer & Explanation
The correct answer is C: These risks can be added to a low priority risk watch list.. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won't affect your project much if they happen. What should you do with these identified risk events?
Options
- AAll risks must have a valid, documented risk response.
- BThese risks can be accepted.
- CThese risks can be added to a low priority risk watch list.
- DThese risks can be dismissed.
Topics
#Risk identification#Risk response strategies#Risk watchlist#Low priority risks
Community Discussion
No community discussion yet for this question.