PMI-RMP · Question #41
You are the project manager of a new project in your organization. You and the project team have identified the project risks, completed risk analysis, and are planning the most appropriate risk…
The correct answer is D. Decision tree analysis. Decision tree analysis is the most effective tool for selecting risk responses because it quantifies the expected monetary value (EMV) of each possible response option. It maps out possible decisions and their outcomes (including probabilities and costs), allowing the project…
Question
You are the project manager of a new project in your organization. You and the project team have identified the project risks, completed risk analysis, and are planning the most appropriate risk responses. Which of the following tools is most effective to choose the most appropriate risk response?
Options
- ACause-and-effect diagrams
- BProject network diagrams
- CDelphi Technique
- DDecision tree analysis
How the community answered
(25 responses)- A8% (2)
- B16% (4)
- C4% (1)
- D72% (18)
Explanation
Decision tree analysis is the most effective tool for selecting risk responses because it quantifies the expected monetary value (EMV) of each possible response option. It maps out possible decisions and their outcomes (including probabilities and costs), allowing the project manager to compare the net expected value of different response strategies side by side. Cause-and-effect diagrams identify root causes of problems, project network diagrams show task sequencing, and the Delphi Technique gathers expert consensus - none of these are designed to evaluate and compare the financial value of competing risk response options.