nerdexam
PMIPMI

PMI-RMP · Question #41

PMI-RMP Question #41: Real Exam Question with Answer & Explanation

The correct answer is D: Decision tree analysis. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You are the project manager of a new project in your organization. You and the project team have identified the project risks, completed risk analysis, and are planning the most appropriate risk responses. Which of the following tools is most effective to choose the most appropriate risk response?

Options

  • ACause-and-effect diagrams
  • BProject network diagrams
  • CDelphi Technique
  • DDecision tree analysis

Topics

#Risk response planning#Quantitative risk analysis#Decision tree analysis#Expected Monetary Value (EMV)

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions