Risk Strategy and Planning
Question
Rachel is the project manager of the KJH Project for her company. She needs a method to create a quick and simple approach to risk identification to communicate the project risk with the stakeholders. Which one of the following approaches to risk identification should Rachel choose to provide a quick and simple listing of the project risks?
Options
- ADelphi Technique
- BChecklist analysis
- CAssumptions analysis
- DBrainstorming
Topics
#Risk Identification#Checklist Analysis#Risk Management Techniques#Project Risk Management