The correct answer is B: Checklist analysis. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Rachel is the project manager of the KJH Project for her company. She needs a method to create a quick and simple approach to risk identification to communicate the project risk with the stakeholders. Which one of the following approaches to risk identification should Rachel choose to provide a quick and simple listing of the project risks?

Options

  • ADelphi Technique
  • BChecklist analysis
  • CAssumptions analysis
  • DBrainstorming

Topics

#Risk Identification#Checklist Analysis#Risk Management Techniques#Project Risk Management