PMI-RMP · Question #4

Which one of the following is the only output for the qualitative risk analysis process?

The correct answer is C. Risk register updates. According to the PMBOK Guide, the sole output of the Perform Qualitative Risk Analysis process is updates to the Risk Register. These updates include the relative ranking of identified risks, risks grouped by category, causes of risk, trends in qualitative analysis results, and…

Perform Targeted Risk Analysis

Question

Which one of the following is the only output for the qualitative risk analysis process?

Options

  • AEnterprise environmental factors
  • BProject management plan
  • CRisk register updates
  • DOrganizational process assets

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    88% (43)
  • D
    2% (1)

Explanation

According to the PMBOK Guide, the sole output of the Perform Qualitative Risk Analysis process is updates to the Risk Register. These updates include the relative ranking of identified risks, risks grouped by category, causes of risk, trends in qualitative analysis results, and a watchlist of low-priority risks. Enterprise environmental factors and organizational process assets are inputs (not outputs) to many project management processes, including qualitative risk analysis. The project management plan is also an input, not an output of this process.