PMI-RMP · Question #12

PMI-RMP Question #12: Real Exam Question with Answer & Explanation

The correct answer is B: SWOT analysis. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You are working with your project stakeholders to identify risks within the JKP Project. You want to use an approach to engage the stakeholders to increase the breadth of the identified risks by including internally generated risk. Which risk identification approach is most suited for this goal?

Options

  • ADelphi Technique
  • BSWOT analysis
  • CAssumptions analysis
  • DBrainstorming

Topics

#Risk identification#SWOT analysis#Internal risks#Risk identification techniques