PMI-RMP Exam Questions
647 real PMI-RMP exam questions with expert-verified answers and explanations. Page 7 of 13.
- Question #302Risk Strategy and Planning
The risk manager wants to determine what is to be measured, how it is to be measured, and what project outcomes are to be measured. In which of the following processes should this...
Risk Management PlanningRisk MeasurementProject Management ProcessesRisk Metrics - Question #303Perform Targeted Risk Analysis
What quantitative tools and techniques are used to perform risk analysis in order to support stakeholder decision making for the project?
Quantitative Risk AnalysisData GatheringInterviewingRisk Analysis Techniques - Question #304Risk Strategy and Planning
While creating the appropriate risk strategy, the project manager discovers that the project team lacks the necessary expertise to define the risk management plan. What additional...
Risk Management PlanExpert JudgmentOrganizational Process AssetsStakeholder Risk Tolerance - Question #305Risk Strategy and Planning
What are critical success factors for the Plan Risk Responses process?
Plan Risk ResponsesCritical Success FactorsRisk Response PlanningRoles and Responsibilities - Question #306Risk Strategy and Planning
A risk is identified and documented by the risk manager, but it is unclear how this risk can be proactively managed. In this situation, what type of reserve should be allocated for...
Risk reservesContingency reserveKnown-unknownsRisk response planning - Question #307Perform Targeted Risk Analysis
A regional vendor for custom manufactured steel oil derricks is awarded a contract to design, manufacture, and install 40 offshore oil platforms. Installation of these derricks req...
Quantitative Risk AnalysisSchedule RiskProbability CalculationIncentive Management - Question #308Risk Strategy and Planning
To properly ensure risk information is incorporated into the overall project management framework, risk data must be provided to the schedule analysts and cost estimators on a peri...
Risk planningRisk management planRisk communicationIntegration of risk data - Question #309Risk Strategy and Planning
What best describes the job of a risk owner?
Risk OwnerRoles and ResponsibilitiesRisk AccountabilityRisk Management Plan - Question #310Risk Monitoring and Reporting
Upon returning from vacation, the risk manager observes during the project status meeting that several activities being accomplished were not in the original plan. What should the...
Change controlScope managementRisk monitoringProject governance - Question #311Perform Targeted Risk Analysis
Contingency Reserve Total: US$213,000 Due to a mitigation strategy, Risk 4's probability has been reduced to 40%. What would be the new contingency reserve total?
Contingency ReserveExpected Monetary Value (EMV)Risk MitigationQuantitative Risk Analysis - Question #312Risk Strategy and Planning
The risk manager examines the enterprise environmental factors to gain an understanding of the stakeholders' risk appetite. However, risk appetites are not determined. What is the...
Risk AppetiteStakeholder EngagementInformation GatheringRisk Planning - Question #313Risk Monitoring and Reporting
During the risk Monitor and Control Project Work process, the scope, schedule, and cost begin to increase. What outputs should be updated and/or created?
Monitor RisksChange ManagementProject BaselinesProject Documents - Question #314Perform Targeted Risk Analysis
During a weekly project review meeting, a stakeholder identifies some new risks. When creating risk responses for these newly identified risks, what should the project team do to d...
Risk Response PlanningRoot Cause AnalysisRisk TrendsEfficient Risk Management - Question #315Risk Monitoring and Reporting
A risk manager is conducting a risk audit review at project completion. Which of the following represents the order that the steps should be performed to complete the full risk aud...
Risk AuditRisk Management ProcessProject ClosureLessons Learned - Question #316Risk Monitoring and Reporting
What is a project issue within a project environment?
Project IssueRisk vs IssueThreatRisk Occurrence - Question #317Perform Targeted Risk Analysis
Which analysis method has a lower standard deviation?
Latin Hypercube SamplingMonte Carlo SimulationQuantitative Risk AnalysisVariance Reduction - Question #318Risk Monitoring and Reporting
A project in the execution phase at the customer's site has an issue concerning new parts that do not fit properly into a machine. The site project manager cannot find this high pr...
Risk AuditingRisk Management Process EffectivenessUnidentified RisksIssue Management - Question #319Perform Targeted Risk Analysis
When performing integrated cost-schedule risk analysis, a risk manager must correlate the project costs and activities with the risk baseline. Why is determining correlation critic...
Integrated Risk AnalysisCorrelationQuantitative Risk AnalysisCost-Schedule Risk - Question #320Risk Strategy and Planning
During the initial risk planning process, the risk manager and project manager discuss ways to handle known risks. Which project reserve should the project manager use to budget fo...
Contingency reserveKnown risksRisk budgetingProject reserves - Question #321Stakeholder Engagement
The project manager is unable to obtain a global consensus of competing subject matter experts and stakeholders on the project scope. This has caused a one-month delay. What should...
Stakeholder conflictEscalation processScope definitionProject sponsor - Question #322Perform Targeted Risk Analysis
The project sponsor has asked the project manager how much more a P90 will cost. The sponsor has budgeted for a P40. The project values are in thousands. How much additional fundin...
Probabilistic Cost EstimationContingency ReserveFunding RequirementsQuantitative Risk Analysis - Question #323Risk Strategy and Planning
The risk manager for a construction project graphically groups project risks by the subsets of economic risk, social risk, and technical risk. Where has this information been captu...
Risk Breakdown StructureRisk CategorizationRisk Planning - Question #324Risk Monitoring and Reporting
At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks had occurred, and the impact was significantly larger than expe...
Risk AuditLessons LearnedProcess ImprovementRisk Monitoring and Control - Question #325Risk Strategy and Planning
During a project review meeting, an executive scrutinizes the risk section, including risks on the watch list, and demands action to close them out. What is the executive's risk at...
Risk attitudeStakeholder risk toleranceRisk aversionWatch list management - Question #326Risk Monitoring and Reporting
A risk manager schedules a project overview meeting with the project sponsor to provide an update on risk management progress. Each functional lead is identifying the most critical...
Risk CommunicationStakeholder ReportingExecutive ReportingRisk Responses - Question #327Risk Strategy and Planning
A project manager is developing the risk management process and schedules a risk planning workshop at the start of the project. Upon receiving the invitation, a senior stakeholder...
Risk management principlesStakeholder managementRisk management planProject management value - Question #328Risk Monitoring and Reporting
When monitoring the execution quality of risk-related plans and processes, which of the following would be a useful metric to track and record?
Risk MonitoringPerformance MetricsRisk Response ImplementationExecution Quality - Question #329Risk Strategy and Planning
What is defined as "an uncertainty that could have a positive or negative effect on the project objectives", and second, what is a "chosen state of mind, mental view or disposition...
Risk DefinitionRisk AttitudeFundamental Concepts - Question #330Risk Monitoring and Reporting
Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?
Organizational Process Assets (OPA)Lessons LearnedRisk Response EffectivenessChange Management Records - Question #331Perform Targeted Risk Analysis
Which input could be utilized to perform quantitative risk analysis to reduce uncertainty?
Quantitative Risk AnalysisOrganizational Process Assets (OPAs)Risk Management InputsUncertainty Reduction - Question #332Risk Strategy and Planning
The risk management process can be defined as which of the following?
Risk Management ProcessIterative ProcessProject LifecycleProcess Characteristics - Question #333Risk Strategy and Planning
The feasibility of the risk management planning is dependent upon which of the following aspects of the organization?
Risk management planningOrganizational capabilitiesOrganizational cultureFeasibility assessment - Question #334Perform Targeted Risk Analysis
The project manager has asked for the P50 estimate for the project schedule. What is the P50 estimate?
P-estimatesSchedule Risk AnalysisQuantitative Risk AnalysisMonte Carlo Simulation - Question #335Risk Strategy and Planning
Which of the following will ultimately determine risk thresholds?
Risk ThresholdsRisk AppetiteStakeholder EngagementRisk Planning - Question #336Stakeholder Engagement
Which of the following characteristics would a risk-adverse person or group demonstrate?
Risk aversionRisk attitudesStakeholder risk tolerance - Question #337Perform Targeted Risk Analysis
After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budg...
Risk cost impactCost forecastingEstimate to complete (ETC)Quantitative risk analysis - Question #338Risk Strategy and Planning
Two companies merge. The executive leadership team for the newly formed company hires a project risk manager to integrate both companies' technology platforms into a single global...
Risk Response PlanningRisk Management ProcessStakeholder EngagementRisk Analysis - Question #339Risk Strategy and Planning
A heavy industrial design firm has over US$3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have...
Opportunities ManagementRisk Breakdown Structure (RBS)Risk CaptureRisk Planning - Question #340Risk Strategy and Planning
What is the best source of project information which could result in the reduction of risk?
Risk IdentificationOrganizational Process AssetsLessons LearnedProactive Risk Management - Question #341Perform Targeted Risk Analysis
Which of the following describes a difference between qualitative and quantitative risk analysis?
Qualitative Risk AnalysisQuantitative Risk AnalysisRisk Analysis - Question #342Risk Monitoring and Reporting
A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?
Risk Response StrategiesContingency PlanningIssue ManagementRisk Monitoring and Control - Question #343Perform Targeted Risk Analysis
The project manager must evaluate two separate contractors for a project with an absolute finish date of 15 December. After performing a Monte Carlo assessment on the submitted sch...
Monte Carlo SimulationSchedule Risk AnalysisProbability and Confidence LevelContractor Selection - Question #344Perform Targeted Risk Analysis
Given the output from the Monte Carlo simulation, what is the probability of a successful completion within the project budget?
Monte Carlo SimulationQuantitative Risk AnalysisCost Risk AnalysisProbability Distribution - Question #345Perform Targeted Risk Analysis
The risk manager of a medium-sized project is performing risk response planning with the project team. The proposed action for one specific, primary risk introduces a secondary ris...
Secondary RisksRisk Response PlanningRisk IdentificationRisk Analysis - Question #346Risk Strategy and Planning
A risk facilitator is creating an outline for the risk management plan. To ensure alignment with the project's objectives, and to develop and recommend the project's risk strategy,...
Risk Management PlanningRisk StrategyProject Planning InputsProject Objectives Alignment - Question #347Risk Strategy and Planning
What items should be included in a complex project's risk management plan?
Risk Management PlanPlan componentsRisk planningRisk methodology - Question #348Stakeholder Engagement
Which of the following represents levels of risk attitude?
Risk attitudeRisk appetiteRisk toleranceStakeholder risk preferences - Question #349Stakeholder Engagement
What would be the next step after determining the agreed-upon risk response for a specific risk?
Risk CommunicationStakeholder EngagementRisk Response Implementation - Question #350Perform Targeted Risk Analysis
The project values are in thousands. What is the average cost of the project?
Quantitative Risk AnalysisCost AnalysisFinancial CalculationData Analysis - Question #351Stakeholder Engagement
A project risk manager is concerned about the low performance of risk management on a mission-critical project. After assessing the situation, the risk manager finds that the commu...
Communication effectivenessTeam influenceStakeholder engagementTrust building