PMIPMI
PMI-RMP · Question #337
PMI-RMP Question #337: Real Exam Question with Answer & Explanation
The correct answer is A: Estimate to complete (ETC). See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget. What is the forecasting methodology that should be utilized to calculate the impact?
Options
- AEstimate to complete (ETC)
- BBudget at completion (BAC)
- CEstimate risk completion (ERC)
- DEstimate at completion (EAC)
Topics
#Risk cost impact#Cost forecasting#Estimate to complete (ETC)#Quantitative risk analysis
Community Discussion
No community discussion yet for this question.