nerdexam
PMIPMI

PMI-RMP · Question #337

PMI-RMP Question #337: Real Exam Question with Answer & Explanation

The correct answer is A: Estimate to complete (ETC). See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget. What is the forecasting methodology that should be utilized to calculate the impact?

Options

  • AEstimate to complete (ETC)
  • BBudget at completion (BAC)
  • CEstimate risk completion (ERC)
  • DEstimate at completion (EAC)

Topics

#Risk cost impact#Cost forecasting#Estimate to complete (ETC)#Quantitative risk analysis

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions