PMI
PMI-RMP · Question #337
After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget. What is the fore
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #337. The question stem and answer options stay visible for context.
Perform Targeted Risk Analysis
Question
After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget. What is the forecasting methodology that should be utilized to calculate the impact?
Options
- AEstimate to complete (ETC)
- BBudget at completion (BAC)
- CEstimate risk completion (ERC)
- DEstimate at completion (EAC)
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk cost impact#Cost forecasting#Estimate to complete (ETC)#Quantitative risk analysis