PMIPMI
PMI-RMP · Question #306
PMI-RMP Question #306: Real Exam Question with Answer & Explanation
The correct answer is A: Contingency. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
A risk is identified and documented by the risk manager, but it is unclear how this risk can be proactively managed. In this situation, what type of reserve should be allocated for the risk?
Options
- AContingency
- BManagement
- CBudget
- DResidual
Topics
#Risk reserves#Contingency reserve#Known-unknowns#Risk response planning
Community Discussion
No community discussion yet for this question.