nerdexam
PMIPMI

PMI-RMP · Question #306

PMI-RMP Question #306: Real Exam Question with Answer & Explanation

The correct answer is A: Contingency. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

A risk is identified and documented by the risk manager, but it is unclear how this risk can be proactively managed. In this situation, what type of reserve should be allocated for the risk?

Options

  • AContingency
  • BManagement
  • CBudget
  • DResidual

Topics

#Risk reserves#Contingency reserve#Known-unknowns#Risk response planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions