PMI-RMP · Question #305

What are critical success factors for the Plan Risk Responses process?

The correct answer is B. Define roles and responsibilities, address threats and opportunities, address interaction of risks. The Plan Risk Responses process must: (1) clearly define who owns and implements each response (roles and responsibilities), (2) address both negative risks (threats) and positive risks (opportunities) since responses differ for each, and (3) consider how risks interact, because

Risk Strategy and Planning

Question

What are critical success factors for the Plan Risk Responses process?

Options

  • ACollect high-quality information about risks, address threats and opportunities, address interaction
  • BDefine roles and responsibilities, address threats and opportunities, address interaction of risks
  • CDefine roles and responsibilities, address threats and opportunities, categorize risk causes, and
  • DIdentify appropriate project model, define roles and responsibilities, address threats and

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    91% (32)
  • C
    3% (1)
  • D
    3% (1)

Explanation

The Plan Risk Responses process must: (1) clearly define who owns and implements each response (roles and responsibilities), (2) address both negative risks (threats) and positive risks (opportunities) since responses differ for each, and (3) consider how risks interact, because responses to one risk can affect others. Option A omits roles and responsibilities. Options C and D introduce elements like 'categorize risk causes' or 'identify the appropriate project model' that are more relevant to earlier risk processes (Identify Risks or Plan Risk Management), not Plan Risk Responses.

Topics

#Plan Risk Responses#Critical Success Factors#Risk Response Planning#Roles and Responsibilities