The correct answer is D: Engage the project sponsor/portfolio manager.. See the full explanation below for the reasoning.

Stakeholder Engagement

Question

The project manager is unable to obtain a global consensus of competing subject matter experts and stakeholders on the project scope. This has caused a one-month delay. What should the project manager do next to reduce further delay?

Options

  • AInitiate a scope change request.
  • BSchedule a project kick-off meeting.
  • CSchedule a stakeholder meeting.
  • DEngage the project sponsor/portfolio manager.

Topics

#Stakeholder conflict#Escalation process#Scope definition#Project sponsor