PMIPMI
PMI-RMP · Question #321
PMI-RMP Question #321: Real Exam Question with Answer & Explanation
The correct answer is D: Engage the project sponsor/portfolio manager.. See the full explanation below for the reasoning.
Stakeholder Engagement
Question
The project manager is unable to obtain a global consensus of competing subject matter experts and stakeholders on the project scope. This has caused a one-month delay. What should the project manager do next to reduce further delay?
Options
- AInitiate a scope change request.
- BSchedule a project kick-off meeting.
- CSchedule a stakeholder meeting.
- DEngage the project sponsor/portfolio manager.
Topics
#Stakeholder conflict#Escalation process#Scope definition#Project sponsor
Community Discussion
No community discussion yet for this question.