PMIPMI
PMI-RMP · Question #320
PMI-RMP Question #320: Real Exam Question with Answer & Explanation
The correct answer is B: Contingency reserve. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
During the initial risk planning process, the risk manager and project manager discuss ways to handle known risks. Which project reserve should the project manager use to budget for known risks?
Options
- ABudget reserve
- BContingency reserve
- CChange management reserve
- DRisk reserve
Topics
#Contingency reserve#Known risks#Risk budgeting#Project reserves
Community Discussion
No community discussion yet for this question.