nerdexam
PMIPMI

PMI-RMP · Question #319

PMI-RMP Question #319: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #319. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

When performing integrated cost-schedule risk analysis, a risk manager must correlate the project costs and activities with the risk baseline. Why is determining correlation critical in performing this analysis?

Options

  • ACorrelation strength is determined by the strength of multiple risks affecting one cost or activity.
  • BCorrelation is always negative in projects with high costs.
  • CCorrelation implies causality between project costs and activities.
  • DCorrelation identifies how each project risk affects project costs or activities.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Integrated Risk Analysis#Correlation#Quantitative Risk Analysis#Cost-Schedule Risk
Full PMI-RMP PracticeBrowse All PMI-RMP Questions