nerdexam
PMIPMI

PMI-RMP · Question #322

PMI-RMP Question #322: Real Exam Question with Answer & Explanation

The correct answer is C: US$913,000. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

The project sponsor has asked the project manager how much more a P90 will cost. The sponsor has budgeted for a P40. The project values are in thousands. How much additional funding would the sponsor need to budget for a P90?

Options

  • AUS$9,408,000
  • BUS$8,495,000
  • CUS$913,000
  • DUS$794,000

Topics

#Probabilistic Cost Estimation#Contingency Reserve#Funding Requirements#Quantitative Risk Analysis

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions