nerdexam
PMI

PMI-RMP · Question #342

A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?

The correct answer is C. Implement a contingency or fallback plan. When a project manager decides to 'take no action' on a risk, they are applying the Acceptance risk response strategy. Even under passive acceptance, best practice in risk management dictates that a contingency plan (or fallback plan) should be prepared in advance for…

Risk Monitoring and Reporting

Question

A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?

Options

  • AImplement a workaround.
  • BCreate a change request.
  • CImplement a contingency or fallback plan.
  • DReview the project management plan.

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    80% (20)
  • D
    4% (1)

Explanation

When a project manager decides to 'take no action' on a risk, they are applying the Acceptance risk response strategy. Even under passive acceptance, best practice in risk management dictates that a contingency plan (or fallback plan) should be prepared in advance for identified risks, so the team is not caught entirely unprepared if the risk materializes. A contingency plan is triggered when a specific risk event occurs; a fallback plan is used when the primary response proves insufficient. A workaround (A) is reserved for unplanned, unidentified risks that had no prior response plan. Creating a change request (B) is a process step, not a response strategy. Reviewing the project management plan (D) is too passive and non-actionable when a risk is actively occurring.

Topics

#Risk Response Strategies#Contingency Planning#Issue Management#Risk Monitoring and Control

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice