PMI-RMP · Question #342
A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?
The correct answer is C. Implement a contingency or fallback plan. When a project manager decides to 'take no action' on a risk, they are applying the Acceptance risk response strategy. Even under passive acceptance, best practice in risk management dictates that a contingency plan (or fallback plan) should be prepared in advance for…
Question
A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?
Options
- AImplement a workaround.
- BCreate a change request.
- CImplement a contingency or fallback plan.
- DReview the project management plan.
How the community answered
(25 responses)- A12% (3)
- B4% (1)
- C80% (20)
- D4% (1)
Explanation
When a project manager decides to 'take no action' on a risk, they are applying the Acceptance risk response strategy. Even under passive acceptance, best practice in risk management dictates that a contingency plan (or fallback plan) should be prepared in advance for identified risks, so the team is not caught entirely unprepared if the risk materializes. A contingency plan is triggered when a specific risk event occurs; a fallback plan is used when the primary response proves insufficient. A workaround (A) is reserved for unplanned, unidentified risks that had no prior response plan. Creating a change request (B) is a process step, not a response strategy. Reviewing the project management plan (D) is too passive and non-actionable when a risk is actively occurring.
Topics
Community Discussion
No community discussion yet for this question.