nerdexam
PMIPMI

PMI-RMP · Question #342

PMI-RMP Question #342: Real Exam Question with Answer & Explanation

The correct answer is C: Implement a contingency or fallback plan.. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?

Options

  • AImplement a workaround.
  • BCreate a change request.
  • CImplement a contingency or fallback plan.
  • DReview the project management plan.

Topics

#Risk Response Strategies#Contingency Planning#Issue Management#Risk Monitoring and Control

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions