PMIPMI
PMI-RMP · Question #342
PMI-RMP Question #342: Real Exam Question with Answer & Explanation
The correct answer is C: Implement a contingency or fallback plan.. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?
Options
- AImplement a workaround.
- BCreate a change request.
- CImplement a contingency or fallback plan.
- DReview the project management plan.
Topics
#Risk Response Strategies#Contingency Planning#Issue Management#Risk Monitoring and Control
Community Discussion
No community discussion yet for this question.