nerdexam
PMIPMI

PMI-RMP · Question #343

PMI-RMP Question #343: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #343. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

The project manager must evaluate two separate contractors for a project with an absolute finish date of 15 December. After performing a Monte Carlo assessment on the submitted schedules, the following information is found: Which contractor should be chosen, because of having the highest statistical output?

Options

  • AContractor A should be chosen based on confidence level.
  • BContractor B should be chosen based on probability.
  • CContractor A should be chosen based on probability and confidence level.
  • DContractor B should be chosen based on probability and confidence level.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Monte Carlo Simulation#Schedule Risk Analysis#Probability and Confidence Level#Contractor Selection
Full PMI-RMP PracticeBrowse All PMI-RMP Questions