PMIPMI
PMI-RMP · Question #345
PMI-RMP Question #345: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #345. The question stem and answer options stay visible for context.
Perform Targeted Risk Analysis
Question
The risk manager of a medium-sized project is performing risk response planning with the project team. The proposed action for one specific, primary risk introduces a secondary risk What should the risk manager and the risk owner of the primary risk do about this situation?
Options
- ATake no action, as secondary risks are not important for the successful execution of a project.
- BInform the project manager about the occurrence of a secondary risk and propose to increase the
- CPerform an analysis to calculate the estimated required budget for the secondary risk and
- DProduce an agreed risk description, assess the probability, impacts, and select an appropriate
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Secondary Risks#Risk Response Planning#Risk Identification#Risk Analysis