PMI-RMP · Question #340
What is the best source of project information which could result in the reduction of risk?
The correct answer is C. Review organizational process assets, lessons learned from previous projects similar in nature. Organizational Process Assets (OPAs), particularly lessons learned from previous similar projects, represent the richest and most validated source of risk-reduction information. They contain real-world data on what risks actually occurred, what their impacts were, and what…
Question
What is the best source of project information which could result in the reduction of risk?
Options
- ADetermine the risks by using brainstorming techniques.
- BSensitivity analysis.
- CReview organizational process assets, lessons learned from previous projects similar in nature.
- DMake observations/conversations on the current projects.
How the community answered
(48 responses)- A6% (3)
- B4% (2)
- C88% (42)
- D2% (1)
Explanation
Organizational Process Assets (OPAs), particularly lessons learned from previous similar projects, represent the richest and most validated source of risk-reduction information. They contain real-world data on what risks actually occurred, what their impacts were, and what responses worked - enabling the current project to proactively avoid or mitigate the same pitfalls. Brainstorming (A) generates new ideas but lacks the empirical grounding of historical data. Sensitivity analysis (B) is a quantitative technique that ranks risks by their relative impact, but it does not identify new risk-reduction strategies. Observations/conversations on current projects (D) provide real-time insight but are limited to present-day experience and miss the depth of cross-project historical data.
Topics
Community Discussion
No community discussion yet for this question.