nerdexam
PMIPMI

PMI-RMP · Question #339

PMI-RMP Question #339: Real Exam Question with Answer & Explanation

The correct answer is A: Integrate them into the RBS.. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

A heavy industrial design firm has over US$3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project. What is the most effective method to capture these opportunities?

Options

  • AIntegrate them into the RBS.
  • BSchedule a project team meeting.
  • CFormally notify the project manager.
  • DEstablish a contingency reserve.

Topics

#Opportunities Management#Risk Breakdown Structure (RBS)#Risk Capture#Risk Planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions