nerdexam
PMI

PMI-RMP · Question #334

The project manager has asked for the P50 estimate for the project schedule. What is the P50 estimate?

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #334. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

The project manager has asked for the P50 estimate for the project schedule. What is the P50 estimate?

Exhibit

PMI-RMP question #334 exhibit

Options

  • A75 days
  • B73.5 days
  • C73 days
  • D72.5 days

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#P-estimates#Schedule Risk Analysis#Quantitative Risk Analysis#Monte Carlo Simulation
Full PMI-RMP Practice