nerdexam
PMIPMI

PMI-RMP · Question #334

PMI-RMP Question #334: Real Exam Question with Answer & Explanation

The correct answer is C: 73 days. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

The project manager has asked for the P50 estimate for the project schedule. What is the P50 estimate?

Options

  • A75 days
  • B73.5 days
  • C73 days
  • D72.5 days

Topics

#P-estimates#Schedule Risk Analysis#Quantitative Risk Analysis#Monte Carlo Simulation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions