PMIPMI
PMI-RMP · Question #334
PMI-RMP Question #334: Real Exam Question with Answer & Explanation
The correct answer is C: 73 days. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
The project manager has asked for the P50 estimate for the project schedule. What is the P50 estimate?
Options
- A75 days
- B73.5 days
- C73 days
- D72.5 days
Topics
#P-estimates#Schedule Risk Analysis#Quantitative Risk Analysis#Monte Carlo Simulation
Community Discussion
No community discussion yet for this question.