nerdexam
PMIPMI

PMI-RMP · Question #335

PMI-RMP Question #335: Real Exam Question with Answer & Explanation

The correct answer is B: The risk appetite of the key stakeholders. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Which of the following will ultimately determine risk thresholds?

Options

  • AThe absolute value of the consequence
  • BThe risk appetite of the key stakeholders
  • CThe practice standard for risk management
  • DThe project manager

Topics

#Risk Thresholds#Risk Appetite#Stakeholder Engagement#Risk Planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions