PMIPMI
PMI-RMP · Question #335
PMI-RMP Question #335: Real Exam Question with Answer & Explanation
The correct answer is B: The risk appetite of the key stakeholders. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Which of the following will ultimately determine risk thresholds?
Options
- AThe absolute value of the consequence
- BThe risk appetite of the key stakeholders
- CThe practice standard for risk management
- DThe project manager
Topics
#Risk Thresholds#Risk Appetite#Stakeholder Engagement#Risk Planning
Community Discussion
No community discussion yet for this question.