PMIPMI
PMI-RMP · Question #308
PMI-RMP Question #308: Real Exam Question with Answer & Explanation
The correct answer is A: As defined in the risk plan. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
To properly ensure risk information is incorporated into the overall project management framework, risk data must be provided to the schedule analysts and cost estimators on a periodic basis. How frequently should this be performed?
Options
- AAs defined in the risk plan
- BAt least once per month
- CAt the end of the financial quarter
- DAs defined in the company standards
Topics
#Risk planning#Risk management plan#Risk communication#Integration of risk data
Community Discussion
No community discussion yet for this question.