PMI-RMP · Question #308
To properly ensure risk information is incorporated into the overall project management framework, risk data must be provided to the schedule analysts and cost estimators on a periodic basis. How freq
The correct answer is A. As defined in the risk plan. The Risk Management Plan is the authoritative document that governs all risk-related processes, including timing and frequency of risk data sharing. Every project is unique, so prescribing a fixed interval (monthly, quarterly) is inappropriate. The risk plan, tailored to the proj
Question
To properly ensure risk information is incorporated into the overall project management framework, risk data must be provided to the schedule analysts and cost estimators on a periodic basis. How frequently should this be performed?
Options
- AAs defined in the risk plan
- BAt least once per month
- CAt the end of the financial quarter
- DAs defined in the company standards
How the community answered
(28 responses)- A86% (24)
- B7% (2)
- C4% (1)
- D4% (1)
Explanation
The Risk Management Plan is the authoritative document that governs all risk-related processes, including timing and frequency of risk data sharing. Every project is unique, so prescribing a fixed interval (monthly, quarterly) is inappropriate. The risk plan, tailored to the project's size, complexity, and stakeholder needs, defines the appropriate reporting cadence. Options B (monthly) and C (quarterly) impose arbitrary organizational schedules that may not fit the project lifecycle. Option D (company standards) is a secondary input; the project-level risk plan takes precedence for project-specific decisions.
Topics
Community Discussion
No community discussion yet for this question.