nerdexam
PMIPMI

PMI-RMP · Question #308

PMI-RMP Question #308: Real Exam Question with Answer & Explanation

The correct answer is A: As defined in the risk plan. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

To properly ensure risk information is incorporated into the overall project management framework, risk data must be provided to the schedule analysts and cost estimators on a periodic basis. How frequently should this be performed?

Options

  • AAs defined in the risk plan
  • BAt least once per month
  • CAt the end of the financial quarter
  • DAs defined in the company standards

Topics

#Risk planning#Risk management plan#Risk communication#Integration of risk data

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions