PMI-RMP Exam Questions
647 real PMI-RMP exam questions with expert-verified answers and explanations. Page 8 of 13.
- Question #352Risk Process Facilitation
What is the purpose of mitigating negative risks as a part of the risk response process?
Risk Response StrategiesRisk MitigationThreatsImpact Reduction - Question #353Risk Strategy and Planning
The engineering department offers the project manager some highly-skilled resources for the same cost as those currently on board. What should the project manager do next to handle...
Positive RiskOpportunity ExploitationImpact AnalysisRisk Response Strategy - Question #354Perform Targeted Risk Analysis
The risk manager is about to go on medical leave, but before departing, conducts a risk response planning review meeting with stakeholders. A new risk manager is assigned to the pr...
Risk Reserve AnalysisIssue IdentificationContingency PlanningRisk Manager Handoff - Question #355Risk Strategy and Planning
Company A sells a new machine to company B. During the risk assessment, the stakeholders of company A do not want the risk of transporting the machine from their facility. Instead,...
Risk Response StrategiesTransfer StrategyLiability AllocationProcurement Risk - Question #356Risk Strategy and Planning
When analyzing the reward system in a company, there is evidence that "fire-fighter behavior" is the highest rewarded behavior. It suggests that people are dealing with major probl...
Organizational CultureReward SystemsProactive Risk ManagementRisk Prevention - Question #357Perform Targeted Risk Analysis
A project manager wants to represent the distribution of uncertainty around a risk model element. However, good data on the variability, of the risk model element has not been coll...
Probability distributionsPERT analysisRisk quantificationBeta distribution - Question #358Risk Strategy and Planning
A mobile operator wants to test a new network prototype before conducting full implementation on the entire network. What type of risk response strategy did the mobile operator cho...
Risk Response StrategiesRisk AvoidancePrototype TestingRisk Validation - Question #359Risk Monitoring and Reporting
The risk register is developed during the initial phases of a virtualized desktop deployment. The register is reviewed by peers, responses are planned, reviewed again, and risks ar...
Risk monitoring and controlRisk register maintenanceRisk response executionProject execution phase - Question #360Perform Targeted Risk Analysis
A well established project begins to experience cost overruns and falls behind schedule. The project risk register identifies many risks and risk response plans in place, yet many...
risk analysis qualityroot cause analysisrisk response effectivenessrisk monitoring and control - Question #361Risk Process Facilitation
Which of the following is an effective channel for risk mitigation assistance, project risk visibility and risk escalation support?
Change Control BoardRisk EscalationRisk GovernanceChange Management - Question #362Stakeholder Engagement
The team has just completed a risk response planning session and identified responses for all the high and medium priority risks. What should the team do with the remaining low pri...
Risk Response PlanningLow Priority Risk ManagementStakeholder EngagementRisk Process Completeness - Question #363Stakeholder Engagement
Which of the following should multicultural groups be aware of on a project relative to risk?
Multicultural teamsRisk attitudesCultural differencesStakeholder perception - Question #364Risk Monitoring and Reporting
A six-month, US$1,2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown ris...
Risk Process ImprovementRisk Response MonitoringResource AllocationRisk Manager Role - Question #365Risk Monitoring and Reporting
The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?
Risk Monitoring and ReportingRisk Breakdown Structure (RBS)Schedule MetricsRisk Analysis - Question #366Perform Targeted Risk Analysis
The risk manager evaluates two contractors, contractor A and contractor B, for a project with a finish date of 15 December. The contractors' bids are the same, including the cost....
Monte Carlo AnalysisSchedule Risk AnalysisRisk Response SelectionCost-Benefit Analysis - Question #367Risk Monitoring and Reporting
A project manager is running a high-cost telecommunications project. There is a monthly status meeting, and the risk manager should provide an update to the project team and projec...
Risk reportingRisk monitoringStatus meetingsStakeholder communication - Question #368Stakeholder Engagement
When considering human factors and risk attitudes relative to the risk process, which approach should be used to influence the risk management process for optimal effects at the in...
Human FactorsRisk AttitudesProactive ApproachInfluencing Stakeholders - Question #369Risk Process Facilitation
Which of the following is the primary project artifact used to capture risks, strategies, ownership patterns, and other vital information about an organization's project risk basel...
Risk RegisterProject ArtifactsRisk Information ManagementRisk Baseline - Question #370Risk Monitoring and Reporting
During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customers electrical infrastructure. This event...
Risk responseWorkaroundUnidentified risksProject execution - Question #371Risk Monitoring and Reporting
Which of the following demonstrates that a company's risk management process is successful?
Risk Management Success MetricsValue of Risk ManagementPerformance Measurement - Question #372Risk Monitoring and Reporting
The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database. A ) Effectiveness of risk response B ) Unexpected or undocumen...
Monitor Risks processLessons LearnedRisk management outputsRisk response effectiveness - Question #373Perform Targeted Risk Analysis
For the last several months, a project manager for a global technology program is focused on improving the project outsourcing process and analyzing the vendor supply chain as key...
Cost-risk sensitivity analysisQuantitative Risk AnalysisRisk PrioritizationCost Management - Question #374Stakeholder Engagement
A company is executing a high-visibility project to develop mobile phone technology. The project sponsor is concerned that an overall high risk rating may undermine support for the...
Ethical decision-makingStakeholder communicationRisk data integrityProfessional conduct - Question #375Stakeholder Engagement
The risk manager organizes a stakeholder meeting to obtain agreement on project risk response strategies. At the conclusion of this meeting, the risk response strategies should be...
Risk response planningStakeholder agreementRisk response implementationActionable risk responses - Question #376Risk Monitoring and Reporting
As a result of the Control Risk process, the project manager updates the project risk documents using outcomes from which of the following?
Control Risk ProcessRisk MonitoringRisk Documentation UpdatesRisk Analysis - Question #377Perform Targeted Risk Analysis
A risk manager assessed all project risks, and the team is now identifying common groupings of risks. What tool or technique is used to perform this risk assessment?
Risk Breakdown Structure (RBS)Risk CategorizationRisk GroupingQualitative Risk Analysis - Question #378Risk Strategy and Planning
A project is in the planning phase, and the risk manager establishes the risk management for the project. Which success factors should be taken into account by the risk manager to...
Risk management planningSuccess factorsProcess integrationOrganizational commitment - Question #379Perform Targeted Risk Analysis
After years of experience, a project manager becomes the lead manager for a company. This new lead manager asks all project managers to use a specific technique when they perform q...
Qualitative Risk AnalysisRisk Analysis TechniquesObjective PrioritizationDecision Making Techniques - Question #380Perform Targeted Risk Analysis
A regional vendor for custom manufactured steel oil derricks, is awarded a contract to design, manufacture, and install 40 offshore oil platforms. Installation of these derricks re...
Quantitative Risk AnalysisSchedule Risk AnalysisMonte Carlo SimulationPERT Analysis - Question #381Perform Targeted Risk Analysis
A risk manager works with the project team, senior management team, subject matter experts and other stakeholders to identify the project risks. Which of the following tools/method...
Decision Tree AnalysisQuantitative Risk AnalysisProject ObjectivesDecision Making Under Uncertainty - Question #382Stakeholder Engagement
During a status meeting, a functional manager complains that the server backup failed, impacting the department. This was a known risk documented in the risk register as an accepte...
Stakeholder analysisRisk identificationStakeholder engagementRisk planning - Question #383Risk Strategy and Planning
A project manager has a two-month project with three project team members. The project sponsor does not agree with the project manager that a risk planning process is necessary, si...
Risk Management FundamentalsScalability of Risk ManagementProject PlanningPM Responsibility - Question #384Perform Targeted Risk Analysis
In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk r...
Qualitative Risk AnalysisProbability AssessmentImpact AssessmentRisk Characterization - Question #385Stakeholder Engagement
A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes...
Stakeholder ManagementRisk CommunicationExecutive Sponsor AlignmentSchedule Management - Question #386Risk Monitoring and Reporting
Which of the following could be included in risk monitoring and controlling techniques?
Risk monitoring techniquesRisk control techniquesEarned Value AnalysisVariance and Trend Analysis - Question #387Risk Monitoring and Reporting
Project stakeholders identify, analyze, and plan the risk responses for a project. However, the contingency reserves are depleted before the project is completed. What recommendati...
Contingency ReservesRisk MonitoringReserve ManagementRisk Control - Question #388Risk Monitoring and Reporting
During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customer's electrical infrastructure. This event...
Contingency ReserveRisk Response ImplementationFunding Identified RisksKnown-Unknown Risks - Question #389Risk Strategy and Planning
Which of the following situational factors has a significant effect on risk attitude?
Risk attitudeRisk perceptionSituational factorsProbability and impact - Question #390Risk Strategy and Planning
A risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex, but has rigorous implementation timelines, and very little c...
Risk Impact ScaleProject PerformanceRisk PrioritizationRisk Planning - Question #391Risk Monitoring and Reporting
A risk is identified early in the project. After six months, itis determined that the risk does not apply to this particular project. How should the risk be handled by the risk man...
Risk closureRisk register managementRisk monitoringFormal risk process - Question #392Stakeholder Engagement
Very low = 1, Low = 2, Moderate = 3, High = 4, Very High = 5. A project manager must complete a report for a stakeholder who is concerned about the possibility of a funding shortfa...
Risk communicationStakeholder engagementRisk reportingCommunication strategy - Question #393Risk Strategy and Planning
What is risk tolerance?
risk tolerancerisk appetiterisk management fundamentals - Question #394Perform Targeted Risk Analysis
Which tool can the project risk manager utilize to help identify and assess project risks?
Risk IdentificationRisk AssessmentData GatheringTools and Techniques - Question #395Stakeholder Engagement
Which of the following characteristics would a risk-tolerant person or group demonstrate?
Risk toleranceStakeholder risk attitudeRisk appetite - Question #396Risk Strategy and Planning
During a major project review, the project manager discovers that large groups of internal management issues are obstructing progress. In reviewing the risk management plan, the pr...
Risk management planStakeholder collaborationRisk categoriesProject governance - Question #397Risk Strategy and Planning
The project manager needs to create a risk management plan for a high risk project, but the company's senior management does not see value in spending time documenting major risks...
Risk Management PlanningStakeholder EngagementSponsor ManagementOvercoming Resistance - Question #398Perform Targeted Risk Analysis
Based on this information, which of the following has the highest risk exposure?
Risk exposureRisk analysisRisk prioritizationProject risks - Question #399Perform Targeted Risk Analysis
The company board is concerned about potential legal action from a high-risk project. What technique can be used to justify risk response decisions taken on this project?
Decision tree analysisQuantitative risk analysisRisk response justificationRisk response selection - Question #400Risk Strategy and Planning
A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits...
Risk Management Plan UpdateOpportunity IdentificationProject Fast-trackingStakeholder Engagement - Question #401Perform Targeted Risk Analysis
Which analysis method uses stratified sampling without replacement?
Sampling techniquesLatin Hypercube SamplingQuantitative risk analysisSimulation