nerdexam
PMIPMI

PMI-RMP · Question #372

PMI-RMP Question #372: Real Exam Question with Answer & Explanation

The correct answer is A: A, B, C. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database. A ) Effectiveness of risk response B ) Unexpected or undocumented risks which occur C ) Relevant risk data D ) Management reserve report Which of the following should be included?

Options

  • AA, B, C
  • BA, C, D
  • CB, C, D
  • DA, B, D

Topics

#Monitor Risks process#Lessons Learned#Risk management outputs#Risk response effectiveness

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions