PMI-RMP · Question #372
The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database. A ) Effectiveness of risk response B ) Unexpected or undocumented risks which occu
The correct answer is A. A, B, C. The Monitor Risks process feeds the lessons learned database with three key outputs: A) Effectiveness of risk responses - documenting what worked or failed improves future risk planning; B) Unexpected or undocumented risks that occurred - capturing surprises helps organizations i
Question
The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database. A ) Effectiveness of risk response B ) Unexpected or undocumented risks which occur C ) Relevant risk data D ) Management reserve report Which of the following should be included?
Options
- AA, B, C
- BA, C, D
- CB, C, D
- DA, B, D
How the community answered
(59 responses)- A90% (53)
- B3% (2)
- C5% (3)
- D2% (1)
Explanation
The Monitor Risks process feeds the lessons learned database with three key outputs: A) Effectiveness of risk responses - documenting what worked or failed improves future risk planning; B) Unexpected or undocumented risks that occurred - capturing surprises helps organizations identify risk blind spots; C) Relevant risk data - actual performance data provides empirical evidence for future risk modeling. Option D, the Management Reserve Report, is a financial/budget control document tied to contingency reserves and is not a standard output of the Monitor Risks lessons learned process. Therefore, A, B, and C (Option A) is correct.
Topics
Community Discussion
No community discussion yet for this question.