nerdexam
PMI

PMI-RMP · Question #372

The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database. A ) Effectiveness of risk response B ) Unexpected or undocumented risks which occu

The correct answer is A. A, B, C. The Monitor Risks process feeds the lessons learned database with three key outputs: A) Effectiveness of risk responses - documenting what worked or failed improves future risk planning; B) Unexpected or undocumented risks that occurred - capturing surprises helps organizations i

Risk Monitoring and Reporting

Question

The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database. A ) Effectiveness of risk response B ) Unexpected or undocumented risks which occur C ) Relevant risk data D ) Management reserve report Which of the following should be included?

Options

  • AA, B, C
  • BA, C, D
  • CB, C, D
  • DA, B, D

How the community answered

(59 responses)
  • A
    90% (53)
  • B
    3% (2)
  • C
    5% (3)
  • D
    2% (1)

Explanation

The Monitor Risks process feeds the lessons learned database with three key outputs: A) Effectiveness of risk responses - documenting what worked or failed improves future risk planning; B) Unexpected or undocumented risks that occurred - capturing surprises helps organizations identify risk blind spots; C) Relevant risk data - actual performance data provides empirical evidence for future risk modeling. Option D, the Management Reserve Report, is a financial/budget control document tied to contingency reserves and is not a standard output of the Monitor Risks lessons learned process. Therefore, A, B, and C (Option A) is correct.

Topics

#Monitor Risks process#Lessons Learned#Risk management outputs#Risk response effectiveness

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice