PMI-RMP Exam Questions
647 real PMI-RMP exam questions with expert-verified answers and explanations. Page 9 of 13.
- Question #402Stakeholder Engagement
A common understanding of the value of risk management among key stakeholders is an effective foundation to managing risk effectively. The project manager should ensure training is...
Stakeholder engagementRisk trainingRisk management valueCommunication - Question #403Risk Strategy and Planning
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area shoul...
Risk response planningResource risksRisk mitigationScope adjustment - Question #404Risk Strategy and Planning
Which of the following is a key element of neuro-linguistic programming?
Neuro-linguistic programmingAgile methodologiesRe-codingChange management - Question #405Risk Process Facilitation
A project manager is creating a risk management plan. The project sponsor does not see the need for additional risk management, believing that the only risks to the project are fin...
Risk IdentificationDelphi TechniqueRisk CategorizationMonte Carlo Analysis - Question #406Risk Strategy and Planning
A risk manager creates a survey for project stakeholders to obtain their opinions on high levels of risk. Key questions in the survey address acceptable levels of cost increases an...
Risk ThresholdsStakeholder InputRisk Planning - Question #407Risk Process Facilitation
Who is the most appropriate person to conduct a risk identification brainstorming session?
Risk identificationBrainstormingFacilitationRoles and responsibilities - Question #408Stakeholder Engagement
The stakeholder is unwilling to make decisions that would result in negative consequences to the project. Which of the following describes the stakeholders attitude regarding proje...
Risk attitudeRisk aversionStakeholder preferencesRisk tolerance - Question #409Risk Monitoring and Reporting
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager...
Management reserveContingency reserveRisk response fundingProject funding - Question #410Risk Strategy and Planning
While preparing for a project review meeting with leadership, the project team analyzes and checks its scope activities and discovers missing requirements. The project risk manager...
Risk ManagementRisk Response StrategiesTransfer RiskSubcontracting - Question #411Risk Strategy and Planning
Which of the following represents the best description of the role of project manager for project risk management?
Project Manager RoleRisk AppetiteRisk ThresholdsStakeholder Consultation - Question #412Perform Targeted Risk Analysis
A race director is planning a marathon with US$80,000 in upfront costs that will be offset by race fees. The remainder of the funds will be donated to a national charity. State law...
Risk MitigationRisk TransferenceRisk Response StrategiesFinancial Risk - Question #413Perform Targeted Risk Analysis
The company is a risk seeking organization, and has experienced measurable success based on their current strategy for growth. A new project has an overall project risk that exceed...
Quantitative Risk AnalysisMonte Carlo SimulationOverall Project RiskRisk Thresholds - Question #414Risk Strategy and Planning
What are the supporting elements for effective risk management?
Effective Risk ManagementEnabling FactorsOrganizational SupportRisk Management Principles - Question #415Perform Targeted Risk Analysis
Which of the following techniques for planning risk response can provide a means of identifying symptoms for use as trigger conditions for contingency responses?
Quantitative Risk AnalysisRisk Response PlanningContingency Triggers - Question #416Risk Strategy and Planning
During what process should a project manager assign a risk owner?
Risk Management PlanningRoles and ResponsibilitiesRisk Owner - Question #417Perform Targeted Risk Analysis
The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks: Risk 1 has a US$500,000 potential cost increase, and...
Expected Monetary Value (EMV)Quantitative Risk AnalysisRisk PrioritizationCost-Benefit Analysis - Question #418Risk Process Facilitation
What identification technique is used to help reduce the ambiguity of a risk statement?
Risk IdentificationRisk Statement ClarityRisk AttributesAmbiguity Reduction - Question #419Perform Targeted Risk Analysis
Which of the following success factors will enhance the Perform Qualitative Risk Analysis process as the risk occurrence gets closer?
Qualitative Risk AnalysisRisk AssessmentSuccess FactorsRisk Definitions - Question #420Risk Strategy and Planning
A stakeholder is asked to approve additional funding to implement a risk response plan. However, the stakeholder is unsure of the amount that could be approved without escalation....
Risk Management PlanApproval AuthorityRisk Response FundingProject Governance - Question #421Perform Targeted Risk Analysis
As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000....
Expected Monetary Value (EMV)Contingency budgetQuantitative risk analysisRisk impact and probability - Question #422Risk Monitoring and Reporting
A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing t...
Risk monitoringRisk response implementationProblem identificationCommunication - Question #423Perform Targeted Risk Analysis
The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being us...
Qualitative Risk AnalysisCognitive BiasesRisk PerceptionFacilitation - Question #424Risk Process Facilitation
A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders in...
Risk identification techniquesNominal Group TechniqueFacilitation techniquesStakeholder interaction - Question #425Risk Monitoring and Reporting
In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; h...
Secondary RisksRisk Response ManagementRisk IdentificationRisk Register - Question #426Perform Targeted Risk Analysis
The project manager wants to use an objective method to evaluate the key project risks and develop response plans. What action should the risk manager propose?
Quantitative Risk AnalysisMonte Carlo AnalysisRisk EvaluationRisk Response Planning - Question #427Risk Strategy and Planning
A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks...
Risk IdentificationPre-project Risk ManagementBid ManagementProject Initiation - Question #428Risk Process Facilitation
A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognize...
Risk manager accountabilitySecondary risksRisk response planningRisk management roles - Question #429Risk Process Facilitation
A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historic...
Risk IdentificationRisk ChecklistLessons LearnedHistorical Information - Question #430Perform Targeted Risk Analysis
During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identifi...
Risk assessmentRisk identificationAssumptions managementDesign phase risks - Question #431Risk Strategy and Planning
An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?
Risk Management PlanProject AccelerationPlan RevisionStrategic Change - Question #432Risk Strategy and Planning
A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include hig...
Risk IdentificationStrategic RiskSWOT AnalysisRisk Planning - Question #433Perform Targeted Risk Analysis
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment What should the risk ma...
Risk identificationRisk analysisTeam collaborationInformation gathering - Question #434Perform Targeted Risk Analysis
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high p...
Risk PrioritizationSensitivity AnalysisRisk Analysis Techniques - Question #435Risk Process Facilitation
The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?
Risk identificationOpportunitiesSWOT analysisRisk workshops - Question #436Risk Monitoring and Reporting
During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting....
Risk Response PlanningSecondary RisksResidual RisksStakeholder Communication - Question #437Perform Targeted Risk Analysis
A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have in...
Enterprise Environmental Factors (EEFs)Risk IdentificationExternal Information SourcesAdaptive Projects - Question #438Risk Strategy and Planning
A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the r...
Risk communicationStrategic risk managementManagement reportingOrganizational impact - Question #439Perform Targeted Risk Analysis
A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors. What sh...
Decision TreeQuantitative Risk AnalysisExpected Monetary ValueOption Evaluation - Question #440Risk Monitoring and Reporting
When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk...
Contingency ReserveRisk Response ImplementationCost OverrunBudget Control - Question #441Risk Process Facilitation
A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analy...
Risk RegisterRisk AttributesQualitative Risk AnalysisRisk Ownership - Question #442Stakeholder Engagement
A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business....
Risk response managementStakeholder communicationRisk thresholdsSponsor engagement - Question #443Risk Monitoring and Reporting
The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the...
Risk response executionRisk register utilizationRisk triggersPlanned responses - Question #444Stakeholder Engagement
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule...
Stakeholder Expectation ManagementRisk CommunicationCommunication PlanningStakeholder Engagement - Question #445Risk Strategy and Planning
A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business...
Agile risk managementDynamic environmentsRisk management approachUncertainty management - Question #446Risk Monitoring and Reporting
While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided...
Secondary RisksRisk IdentificationRisk RegisterRisk Monitoring - Question #447Risk Monitoring and Reporting
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Alt...
Risk Response ImplementationSchedule IntegrationRisk MonitoringAccountability - Question #448Perform Targeted Risk Analysis
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding o...
Qualitative Risk AnalysisRisk AssessmentPMI Risk Management ProcessesLikelihood and Impact - Question #449Stakeholder Engagement
A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, l...
Stakeholder engagementStakeholder analysisUnderstanding stakeholder perspectives - Question #450Perform Targeted Risk Analysis
A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available t...
Quantitative Risk AnalysisRisk SimulationRisk Probability and ImpactRisk Analysis Techniques - Question #451Risk Strategy and Planning
A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team. What two items sho...
Risk IdentificationProject ScopeRisk Management PlanWorkshop Preparation