nerdexam
PMIPMI

PMI-RMP · Question #421

PMI-RMP Question #421: Real Exam Question with Answer & Explanation

The correct answer is B: US$52,000. In risk management, to calculate the contingency budget for risks, we use the Expected Monetary Value (EMV) formula: EMV=Probability of Risk×Impact of Risk\text{EMV} = \text{Probability of Risk} \times \text{Impact of Risk}EMV=Probability of Risk×Impact of Risk Probability: 40% o

Perform Targeted Risk Analysis

Question

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000. What is the total contingency budget that should be created?

Options

  • AUS$68,000
  • BUS$52,000
  • CUS$120,000
  • DUS$80,000

Explanation

In risk management, to calculate the contingency budget for risks, we use the Expected Monetary Value (EMV) formula: EMV=Probability of Risk×Impact of Risk\text{EMV} = \text{Probability of Risk} \times \text{Impact of Risk}EMV=Probability of Risk×Impact of Risk Probability: 40% or 0.40 Impact: US$100,000 \text{EMV of Risk A} = 0.40 \times 100,000 = US$40,000 Probability: 60% or 0.60 Impact: US$20,000 \text{EMV of Risk B} = 0.60 \times 20,000 = US$12,000 Total contingency budget = EMV of Risk A + EMV of Risk B 40,000 + 12,000 = US$52,000 Thus, the total contingency budget required for both risks is US$52,000. This approach follows PMI's risk management guidelines, specifically under the "Quantitative Risk Analysis" process. This process focuses on determining numerical probabilities and monetary impacts to compute the expected financial impact of identified risks.

Topics

#Expected Monetary Value (EMV)#Contingency budget#Quantitative risk analysis#Risk impact and probability

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions