nerdexam
PMI

PMI-RMP · Question #421

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability ris

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #421. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000. What is the total contingency budget that should be created?

Options

  • AUS$68,000
  • BUS$52,000
  • CUS$120,000
  • DUS$80,000

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Expected Monetary Value (EMV)#Contingency budget#Quantitative risk analysis#Risk impact and probability
Full PMI-RMP Practice