PMI-RMP · Question #424

PMI-RMP Question #424: Real Exam Question with Answer & Explanation

The correct answer is D: Nominal group technique. The risk identification technique that the risk manager should use is the nominal group technique. This technique involves bringing stakeholders together to brainstorm potential risks and then ranking them based on their importance. This allows for interaction and collaboration a

Risk Process Facilitation

Question

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created. Which risk identification technique should the risk manager use?

Options

  • APrompt lists
  • BInterviews
  • CDelphi technique
  • DNominal group technique

Explanation

The risk identification technique that the risk manager should use is the nominal group technique. This technique involves bringing stakeholders together to brainstorm potential risks and then ranking them based on their importance. This allows for interaction and collaboration among stakeholders, which can help ensure that an exhaustive list of risks is created. The nominal group technique is a risk identification technique that involves the interaction and collaboration of stakeholders to generate an exhaustive list of risks. It is a structured process that allows each participant to share their ideas independently, then rank and prioritize them as a group. This technique ensures that all opinions are considered and reduces the influence of dominant or biased individuals.

Topics

#Risk identification techniques#Nominal Group Technique#Facilitation techniques#Stakeholder interaction