PMI-RMP · Question #416
During what process should a project manager assign a risk owner?
The correct answer is B. Plan Risk Management. The Plan Risk Management process produces the risk management plan, which defines roles and responsibilities for the risk process-including the criteria and structure for assigning risk owners across the project. By establishing who is accountable for risk ownership at this stage
Question
During what process should a project manager assign a risk owner?
Options
- APlan Risk Responses
- BPlan Risk Management
- CMonitor Risks
- DIdentify Risks
How the community answered
(41 responses)- A2% (1)
- B85% (35)
- C7% (3)
- D5% (2)
Explanation
The Plan Risk Management process produces the risk management plan, which defines roles and responsibilities for the risk process-including the criteria and structure for assigning risk owners across the project. By establishing who is accountable for risk ownership at this stage, the framework is in place before risks are even identified. While individual risk owners are assigned to specific risks later during Plan Risk Responses (A), the governance model and authority for those assignments is established in Plan Risk Management. Identify Risks (D) and Monitor Risks (C) occur too late in the lifecycle to be the appropriate point to define risk owner assignment frameworks.
Topics
Community Discussion
No community discussion yet for this question.