The correct answer is C: Probability risk, impact. See the full explanation below for the reasoning.
Risk Process Facilitation
Question
What identification technique is used to help reduce the ambiguity of a risk statement?
Options
- ADriver risk, outcome
- BExploit, risk, accept
- CProbability risk, impact
- DCause, risk, effect
Topics
#Risk Identification#Risk Statement Clarity#Risk Attributes#Ambiguity Reduction