nerdexam
PMIPMI

PMI-RMP · Question #447

PMI-RMP Question #447: Real Exam Question with Answer & Explanation

The correct answer is D: Updated the project schedule, adding risk owner implementation tasks.. The project manager should have updated the project schedule by adding risk owner implementation tasks. This would have ensured that the planned risk responses were implemented in a timely manner and tracked as part of the project schedule. This would also have allowed the projec

Risk Monitoring and Reporting

Question

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented. What should the project manager have done to avoid this?

Options

  • AProvided regular training to the risk owners for plan implementation
  • BDetermined risk triggers and thresholds in the risk response plan
  • CIncreased communications to influence stakeholder risk responses
  • DUpdated the project schedule, adding risk owner implementation tasks.

Explanation

The project manager should have updated the project schedule by adding risk owner implementation tasks. This would have ensured that the planned risk responses were implemented in a timely manner and tracked as part of the project schedule. This would also have allowed the project manager to monitor the progress of risk response implementation and take corrective action if necessary.

Topics

#Risk Response Implementation#Schedule Integration#Risk Monitoring#Accountability

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions