PMI
PMI-RMP · Question #409
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that ther
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #409. The question stem and answer options stay visible for context.
Risk Monitoring and Reporting
Question
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve. From which of the following sources should the funds be drawn to cover the risk mitigation?
Options
- AOrganization management reserve
- BUnplanned risk reserve
- CContingency reserve
- DManagement reserve
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Management reserve#Contingency reserve#Risk response funding#Project funding