PMIPMI
PMI-RMP · Question #409
PMI-RMP Question #409: Real Exam Question with Answer & Explanation
The correct answer is D: Management reserve. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve. From which of the following sources should the funds be drawn to cover the risk mitigation?
Options
- AOrganization management reserve
- BUnplanned risk reserve
- CContingency reserve
- DManagement reserve
Topics
#Management reserve#Contingency reserve#Risk response funding#Project funding
Community Discussion
No community discussion yet for this question.