nerdexam
PMIPMI

PMI-RMP · Question #409

PMI-RMP Question #409: Real Exam Question with Answer & Explanation

The correct answer is D: Management reserve. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve. From which of the following sources should the funds be drawn to cover the risk mitigation?

Options

  • AOrganization management reserve
  • BUnplanned risk reserve
  • CContingency reserve
  • DManagement reserve

Topics

#Management reserve#Contingency reserve#Risk response funding#Project funding

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions