nerdexam
PMIPMI

PMI-RMP · Question #410

PMI-RMP Question #410: Real Exam Question with Answer & Explanation

The correct answer is B: Transfer. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

While preparing for a project review meeting with leadership, the project team analyzes and checks its scope activities and discovers missing requirements. The project risk manager decides to hire a subcontractor to fulfil these newly discovered requirements. What risk strategy did the project risk manager use?

Options

  • AAvoid
  • BTransfer
  • CAccept
  • DMitigate

Topics

#Risk Management#Risk Response Strategies#Transfer Risk#Subcontracting

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions