PMIPMI
PMI-RMP · Question #410
PMI-RMP Question #410: Real Exam Question with Answer & Explanation
The correct answer is B: Transfer. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
While preparing for a project review meeting with leadership, the project team analyzes and checks its scope activities and discovers missing requirements. The project risk manager decides to hire a subcontractor to fulfil these newly discovered requirements. What risk strategy did the project risk manager use?
Options
- AAvoid
- BTransfer
- CAccept
- DMitigate
Topics
#Risk Management#Risk Response Strategies#Transfer Risk#Subcontracting
Community Discussion
No community discussion yet for this question.