Which of the following represents the best description of the role of project manager for project risk management?
The correct answer is B. Determining the acceptable levels of risk for the project in consultation with stakeholders. The project manager's primary role in risk management is to determine acceptable risk levels in consultation with stakeholders - this involves facilitating stakeholder engagement, setting risk thresholds, and ensuring the risk management plan reflects the organization's and…
Question
Which of the following represents the best description of the role of project manager for project risk management?
Options
- ADetermining the acceptable levels of risk for the project in consultation with stakeholders,
- BDetermining the acceptable levels of risk for the project in consultation with stakeholders,
- CApproving the risk management plan, participating in all aspects of the project risk management
- DDetermining the acceptable levels of risk for the project in consultation with stakeholders,
How the community answered
(29 responses)- A7% (2)
- B90% (26)
- D3% (1)
Explanation
The project manager's primary role in risk management is to determine acceptable risk levels in consultation with stakeholders - this involves facilitating stakeholder engagement, setting risk thresholds, and ensuring the risk management plan reflects the organization's and sponsor's tolerance. Option C describes approving the risk management plan and participating in all aspects of risk management; plan approval is typically the sponsor's responsibility, not the PM's. Options A, B, and D appear to share similar text (a formatting artifact in this question), but B represents the most accurate description of the PM's core risk governance role: stakeholder-informed risk threshold setting and oversight.