PMI-RMP · Question #411
PMI-RMP Question #411: Real Exam Question with Answer & Explanation
The correct answer is B: Determining the acceptable levels of risk for the project in consultation with stakeholders,. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Which of the following represents the best description of the role of project manager for project risk management?
Options
- ADetermining the acceptable levels of risk for the project in consultation with stakeholders,
- BDetermining the acceptable levels of risk for the project in consultation with stakeholders,
- CApproving the risk management plan, participating in all aspects of the project risk management
- DDetermining the acceptable levels of risk for the project in consultation with stakeholders,
Topics
#Project Manager Role#Risk Appetite#Risk Thresholds#Stakeholder Consultation