PMI-RMP · Question #443

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment t

The correct answer is C. Proceed with the planned risk response to move the equipment.. The risk was pre-identified, analyzed, and a response plan was developed and recorded in the risk register. When the risk event (bad weather) actually occurs, the correct action is to execute the planned risk response - that is the entire purpose of proactive risk planning. Clien

Risk Monitoring and Reporting

Question

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway. What should the project manager do?

Options

  • AWait until the weather improves before sending the equipment.
  • BAsk the project sponsor to approve shipping the equipment.
  • CProceed with the planned risk response to move the equipment.
  • DRequest the shipment of the equipment to satisfy the client.

How the community answered

(58 responses)
  • A
    9% (5)
  • B
    2% (1)
  • C
    84% (49)
  • D
    5% (3)

Explanation

The risk was pre-identified, analyzed, and a response plan was developed and recorded in the risk register. When the risk event (bad weather) actually occurs, the correct action is to execute the planned risk response - that is the entire purpose of proactive risk planning. Client pressure does not override an agreed-upon risk response plan. Waiting for weather to improve (A) may be part of the response, but the key principle is that the team follows the documented plan rather than making an ad hoc decision. Bypassing the plan undermines the risk management process.

Topics

#Risk response execution#Risk register utilization#Risk triggers#Planned responses