nerdexam
PMI

PMI-RMP · Question #438

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (

The correct answer is A. Risks that are tied to the success of the organization B. Risks as they apply to the organization's overall risk management philosophy and strategic. When presenting to management, the risk manager should focus on strategic relevance. Risks tied to organizational success (A) speak directly to what executives care about most - mission-critical outcomes. Framing risks within the organization's overall risk philosophy and strateg

Risk Strategy and Planning

Question

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

Options

  • ARisks that are tied to the success of the organization
  • BRisks as they apply to the organization's overall risk management philosophy and strategic
  • CHuge opportunities that possibly bring an additional 30% return for 10 projects in the next year
  • DRisks related to cost that will impact the major projects that are currently in the execution phase
  • ERisk mitigation actions that will require work from stakeholders

How the community answered

(53 responses)
  • A
    79% (42)
  • C
    13% (7)
  • D
    4% (2)
  • E
    4% (2)

Explanation

When presenting to management, the risk manager should focus on strategic relevance. Risks tied to organizational success (A) speak directly to what executives care about most - mission-critical outcomes. Framing risks within the organization's overall risk philosophy and strategic objectives (B) ensures the presentation is aligned with how management views and makes decisions about risk. Option C (30% return across 10 projects) is speculative and overly optimistic, lacking the credibility needed for executive discussion. Option D (cost risks in execution) is too tactical and project-specific. Option E (stakeholder mitigation work) is operational detail, not an executive-level focus.

Topics

#Risk communication#Strategic risk management#Management reporting#Organizational impact

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice