PMI-RMP · Question #451

PMI-RMP Question #451: Real Exam Question with Answer & Explanation

The correct answer is A: Scope of work and requirements. The risk manager should have their team review the scope of work and requirements to ensure they understand the project's objectives and deliverables. Additionally, reviewing the risk management plan will help the team understand the risk management process, roles, and responsibi

Risk Strategy and Planning

Question

A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team. What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)

Options

  • AScope of work and requirements
  • BMonte Carlo analysis from a similar project
  • CList of pre-approved contractors
  • DOrganization chart for city permit department
  • ERisk management plan

Explanation

The risk manager should have their team review the scope of work and requirements to ensure they understand the project's objectives and deliverables. Additionally, reviewing the risk management plan will help the team understand the risk management process, roles, and responsibilities, and prepare for the risk identification workshop. The scope of work and requirements are key inputs for the risk identification process, as they define the project boundaries, deliverables, assumptions, and constraints. The risk management plan is also an essential input, as it provides the guidelines and framework for how risk management will be performed throughout the project.

Topics

#Risk Identification#Project Scope#Risk Management Plan#Workshop Preparation