PMIPMI
PMI-RMP · Question #420
PMI-RMP Question #420: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #420. The question stem and answer options stay visible for context.
Risk Strategy and Planning
Question
A stakeholder is asked to approve additional funding to implement a risk response plan. However, the stakeholder is unsure of the amount that could be approved without escalation. Where should the stakeholder look to determine the amount that can be approved?
Options
- AProject charter
- BRisk management plan
- CRisk register
- DOrganizational process assets
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management Plan#Approval Authority#Risk Response Funding#Project Governance