PMI-RMP · Question #420
A stakeholder is asked to approve additional funding to implement a risk response plan. However, the stakeholder is unsure of the amount that could be approved without escalation. Where should the…
The correct answer is B. Risk management plan. The risk management plan defines the governance structure for risk management, including roles, responsibilities, and authority levels-specifically, the delegation of financial authority for approving risk response expenditures and the thresholds above which escalation is…
Question
A stakeholder is asked to approve additional funding to implement a risk response plan. However, the stakeholder is unsure of the amount that could be approved without escalation. Where should the stakeholder look to determine the amount that can be approved?
Options
- AProject charter
- BRisk management plan
- CRisk register
- DOrganizational process assets
How the community answered
(27 responses)- B89% (24)
- C7% (2)
- D4% (1)
Explanation
The risk management plan defines the governance structure for risk management, including roles, responsibilities, and authority levels-specifically, the delegation of financial authority for approving risk response expenditures and the thresholds above which escalation is required. This is the single authoritative document that establishes who can approve what amount without escalating. The project charter (A) establishes high-level authority but does not typically detail risk-specific funding approval thresholds. The risk register (C) documents individual risks and responses but not approval authority. Organizational process assets (D) provide general corporate policies but the project-specific threshold is in the risk management plan.
Topics
Community Discussion
No community discussion yet for this question.