nerdexam
PMI

PMI-RMP · Question #428

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key seco

The correct answer is B. The risk manager. Secondary risks are new risks that emerge as a direct result of implementing a risk response. Identifying and documenting secondary risks is a core deliverable of risk response planning. The risk manager owns this process and is therefore accountable when secondary risks are miss

Risk Process Facilitation

Question

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered. Who should the project manager hold accountable for missing the risks?

Options

  • AThe audit team
  • BThe risk manager
  • CThe risk owners
  • DThe discipline engineers

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    71% (15)
  • C
    14% (3)
  • D
    10% (2)

Explanation

Secondary risks are new risks that emerge as a direct result of implementing a risk response. Identifying and documenting secondary risks is a core deliverable of risk response planning. The risk manager owns this process and is therefore accountable when secondary risks are missed. The audit team (A) reviews compliance but does not own risk identification. Risk owners (C) are responsible for executing responses, not for discovering secondary risks during planning. Discipline engineers (D) contribute technical input but the accountability for completeness of risk response planning rests with the risk manager.

Topics

#Risk manager accountability#Secondary risks#Risk response planning#Risk management roles

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice