nerdexam
PMI

PMI-RMP · Question #426

The project manager wants to use an objective method to evaluate the key project risks and develop response plans. What action should the risk manager propose?

The correct answer is C. Ask the team to prepare a Monte Carlo analysis.. Monte Carlo analysis is a quantitative risk analysis technique that uses computer simulation to model thousands of possible scenarios by randomly sampling input probability distributions. It produces an objective, statistically grounded probability distribution of project outcome

Perform Targeted Risk Analysis

Question

The project manager wants to use an objective method to evaluate the key project risks and develop response plans. What action should the risk manager propose?

Options

  • AAsk the team to perform an earned value analysis.
  • BReview the lessons learned from other projects.
  • CAsk the team to prepare a Monte Carlo analysis.
  • DAsk the risk expert to perform a PESTLE evaluation.

How the community answered

(41 responses)
  • A
    7% (3)
  • B
    2% (1)
  • C
    78% (32)
  • D
    12% (5)

Explanation

Monte Carlo analysis is a quantitative risk analysis technique that uses computer simulation to model thousands of possible scenarios by randomly sampling input probability distributions. It produces an objective, statistically grounded probability distribution of project outcomes (cost, schedule), making it ideal for objectively evaluating key risks and informing response planning. Earned value analysis (A) measures project performance, not risk probability. Lessons learned (B) is a qualitative, historical input technique. PESTLE (D) is an environmental scanning tool used during risk identification, not quantitative risk evaluation.

Topics

#Quantitative Risk Analysis#Monte Carlo Analysis#Risk Evaluation#Risk Response Planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice