nerdexam
PMIPMI

PMI-RMP · Question #435

PMI-RMP Question #435: Real Exam Question with Answer & Explanation

The correct answer is C: Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis. The risk management plan is a document that describes how risk management activities will be structured and performed on a project. It defines the roles and responsibilities, risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response st

Risk Process Facilitation

Question

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

Options

  • AUse the Delphi technique involving experts who have identified opportunities in the past
  • BInterview more stakeholders who have a positive mindset
  • CConduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis
  • DConduct a political, economic, sociological, technological, legal, and environmental (PESTLE)

Explanation

The risk management plan is a document that describes how risk management activities will be structured and performed on a project. It defines the roles and responsibilities, risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms. The risk management plan should be aligned with the project management plan, which defines the project scope, schedule, cost, quality, and other aspects. When an organization decides to accelerate a key project, it means that the project objectives, assumptions, constraints, and environment have changed. This will affect the risk exposure and profile of the project, as well as the risk management approach and resources. Therefore, the first action for the project risk manager to take is to revise the risk management plan to reflect the new situation and ensure that the risk management process is still effective and efficient. Revising the risk management plan may involve updating the risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms to suit the accelerated project. The project risk manager should also communicate the revised risk management plan to the relevant stakeholders and obtain their approval and support. Ensuring sufficient resources are available, updating the risk register, and meeting with the project's stakeholders are all important actions to take when accelerating a project, but they are not the first action. These actions should be done after revising the risk management plan, as they depend on the updated risk management approach and process. For example, the project risk manager may need to allocate more resources to risk management activities, identify and analyze new or changed risks, implement new or modified risk responses, and report the risk status and performance to the stakeholders based on the revised risk management plan.

Topics

#Risk identification#Opportunities#SWOT analysis#Risk workshops

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions