PMI-RMP · Question #403
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as…
The correct answer is A. Scope reduction to reduce SME reliance. When a key SME is unavailable and causing delivery delays, the root problem is excessive dependency on a single resource. The coaching opportunity is scope reduction - reducing the amount of work that requires that SME breaks the bottleneck and directly addresses the risk…
Question
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?
Options
- AScope reduction to reduce SME reliance
- BRisk management plan and planned risks responses
- CRisk identification process and participation
- DDetailed review of the project schedule before approval
How the community answered
(31 responses)- A71% (22)
- B16% (5)
- C3% (1)
- D10% (3)
Explanation
When a key SME is unavailable and causing delivery delays, the root problem is excessive dependency on a single resource. The coaching opportunity is scope reduction - reducing the amount of work that requires that SME breaks the bottleneck and directly addresses the risk. Options B and C (risk management plan and risk identification) are valid processes but do not address the immediate resource constraint. Option D (schedule review before approval) is a preventive measure, but the delay has already occurred, making scope reduction the actionable response the risk manager should coach toward.