PMI
PMI-RMP · Question #403
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as an
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #403. The question stem and answer options stay visible for context.
Risk Strategy and Planning
Question
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?
Options
- AScope reduction to reduce SME reliance
- BRisk management plan and planned risks responses
- CRisk identification process and participation
- DDetailed review of the project schedule before approval
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk response planning#Resource risks#Risk mitigation#Scope adjustment