PMIPMI
PMI-RMP · Question #403
PMI-RMP Question #403: Real Exam Question with Answer & Explanation
The correct answer is A: Scope reduction to reduce SME reliance. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?
Options
- AScope reduction to reduce SME reliance
- BRisk management plan and planned risks responses
- CRisk identification process and participation
- DDetailed review of the project schedule before approval
Topics
#Risk response planning#Resource risks#Risk mitigation#Scope adjustment
Community Discussion
No community discussion yet for this question.