nerdexam
PMIPMI

PMI-RMP · Question #403

PMI-RMP Question #403: Real Exam Question with Answer & Explanation

The correct answer is A: Scope reduction to reduce SME reliance. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?

Options

  • AScope reduction to reduce SME reliance
  • BRisk management plan and planned risks responses
  • CRisk identification process and participation
  • DDetailed review of the project schedule before approval

Topics

#Risk response planning#Resource risks#Risk mitigation#Scope adjustment

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions