PMI-RMP · Question #366
PMI-RMP Question #366: Real Exam Question with Answer & Explanation
The correct answer is B: Contractor B, based on the probability and confidence levels, as there is a higher cumulative. See the full explanation below for the reasoning.
Question
The risk manager evaluates two contractors, contractor A and contractor B, for a project with a finish date of 15 December. The contractors' bids are the same, including the cost. After performing a Monte Carlo assessment on the contractors' schedules, the risk manager returns the following information: In order for contractor A to meet the finish date of 15 December, it will cost an additional US$750,000, and will not change the confidence level. In order for contractor B to meet the finish date of 15 December, it will cost an additional US$600,000, and will increase the confidence level by 10%. Which contractor should the risk manager select?
Options
- AContractor A, based on the probability and confidence levels, as there is a higher cumulative
- BContractor B, based on the probability and confidence levels, as there is a higher cumulative
- CContractor B, based on costing US$150,000 less than contractor A.
- DContractor A, based on the confidence level.
Topics
Community Discussion
No community discussion yet for this question.