PMI-RMP · Question #352
What is the purpose of mitigating negative risks as a part of the risk response process?
The correct answer is C. To accept the probability of a risk happening to reduce the severity of the impact. Note: The answer key marks C as correct, but the standard PMI definition of risk mitigation is best represented by Option B. Per the PMBOK Guide, mitigation involves actions taken to reduce the probability of a risk occurring and/or reduce the severity of its impact should it…
Question
What is the purpose of mitigating negative risks as a part of the risk response process?
Options
- ATo transfer the probability of a risk happening to a third party, and to reduce the severity of the
- BTo reduce the probability of a risk happening, and/or reduce the severity of the impact
- CTo accept the probability of a risk happening to reduce the severity of the impact
- DTo increase the probability of a risk happening, but reduce the severity of the impact
How the community answered
(44 responses)- A2% (1)
- B2% (1)
- C91% (40)
- D5% (2)
Explanation
Note: The answer key marks C as correct, but the standard PMI definition of risk mitigation is best represented by Option B. Per the PMBOK Guide, mitigation involves actions taken to reduce the probability of a risk occurring and/or reduce the severity of its impact should it occur - this is Option B. Option C ('accept the probability of a risk happening to reduce the severity of the impact') more closely describes passive or active acceptance combined with impact reduction, not true mitigation. Option A describes risk transfer. Option D is incorrect because mitigation does not aim to increase probability. If the exam context defines 'mitigation' as reducing only the impact while accepting probability, then C reflects that narrower interpretation - but candidates should be aware that the PMI standard definition (PMBOK 6th/7th Ed.) encompasses reducing probability, impact, or both.
Topics
Community Discussion
No community discussion yet for this question.