nerdexam
PMIPMI

PMI-RMP · Question #352

PMI-RMP Question #352: Real Exam Question with Answer & Explanation

The correct answer is C: To accept the probability of a risk happening to reduce the severity of the impact. See the full explanation below for the reasoning.

Risk Process Facilitation

Question

What is the purpose of mitigating negative risks as a part of the risk response process?

Options

  • ATo transfer the probability of a risk happening to a third party, and to reduce the severity of the
  • BTo reduce the probability of a risk happening, and/or reduce the severity of the impact
  • CTo accept the probability of a risk happening to reduce the severity of the impact
  • DTo increase the probability of a risk happening, but reduce the severity of the impact

Topics

#Risk Response Strategies#Risk Mitigation#Threats#Impact Reduction

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions