PMIPMI
PMI-RMP · Question #353
PMI-RMP Question #353: Real Exam Question with Answer & Explanation
The correct answer is B: Analyze the impact of replacing the resources and exploit the opportunity.. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
The engineering department offers the project manager some highly-skilled resources for the same cost as those currently on board. What should the project manager do next to handle this situation?
Options
- ACreate a change request to prevent a delay in getting the resources hired.
- BAnalyze the impact of replacing the resources and exploit the opportunity.
- CDecline, to avoid changes in project team setup and stakeholder disruption.
- DAccept the resources, to ensure project efficiency improvement is gained from the new resources.
Topics
#Opportunity Management#Positive Risk Response#Impact Analysis#Resource Management
Community Discussion
No community discussion yet for this question.