nerdexam
PMIPMI

PMI-RMP · Question #353

PMI-RMP Question #353: Real Exam Question with Answer & Explanation

The correct answer is B: Analyze the impact of replacing the resources and exploit the opportunity.. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

The engineering department offers the project manager some highly-skilled resources for the same cost as those currently on board. What should the project manager do next to handle this situation?

Options

  • ACreate a change request to prevent a delay in getting the resources hired.
  • BAnalyze the impact of replacing the resources and exploit the opportunity.
  • CDecline, to avoid changes in project team setup and stakeholder disruption.
  • DAccept the resources, to ensure project efficiency improvement is gained from the new resources.

Topics

#Opportunity Management#Positive Risk Response#Impact Analysis#Resource Management

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions