PMI-RMP · Question #353
The engineering department offers the project manager some highly-skilled resources for the same cost as those currently on board. What should the project manager do next to handle this situation?
The correct answer is B. Analyze the impact of replacing the resources and exploit the opportunity. Option B is correct because a project manager's role includes identifying and exploiting opportunities - receiving highly-skilled resources at the same cost is a positive risk (opportunity) that could improve project outcomes, but it must first be analyzed for schedule…
Question
The engineering department offers the project manager some highly-skilled resources for the same cost as those currently on board. What should the project manager do next to handle this situation?
Options
- ACreate a change request to prevent a delay in getting the resources hired.
- BAnalyze the impact of replacing the resources and exploit the opportunity.
- CDecline, to avoid changes in project team setup and stakeholder disruption.
- DAccept the resources, to ensure project efficiency improvement is gained from the new resources.
How the community answered
(19 responses)- A11% (2)
- B79% (15)
- C5% (1)
- D5% (1)
Explanation
Option B is correct because a project manager's role includes identifying and exploiting opportunities - receiving highly-skilled resources at the same cost is a positive risk (opportunity) that could improve project outcomes, but it must first be analyzed for schedule, quality, and team dynamics impacts before acting.
- A is wrong because no change request is needed yet - you haven't even decided to replace anyone, and a change request skips the required analysis step.
- C is wrong because declining an opportunity without analysis violates risk management principles; avoiding all change is not a project management best practice.
- D is wrong because blindly accepting resources without impact analysis could disrupt the team, affect timelines, or create onboarding overhead - "accept immediately" ignores due diligence.
Memory tip: Think of opportunities like free upgrades - you don't automatically take them OR refuse them; you analyze first, then exploit. The word "exploit" in PMI terminology specifically means taking full advantage of an opportunity, but analysis always comes before action.
Topics
Community Discussion
No community discussion yet for this question.