nerdexam
PMI

PMI-RMP · Question #353

The engineering department offers the project manager some highly-skilled resources for the same cost as those currently on board. What should the project manager do next to handle this situation?

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #353. The question stem and answer options stay visible for context.

Risk Strategy and Planning

Question

The engineering department offers the project manager some highly-skilled resources for the same cost as those currently on board. What should the project manager do next to handle this situation?

Options

  • ACreate a change request to prevent a delay in getting the resources hired.
  • BAnalyze the impact of replacing the resources and exploit the opportunity.
  • CDecline, to avoid changes in project team setup and stakeholder disruption.
  • DAccept the resources, to ensure project efficiency improvement is gained from the new resources.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Positive Risk#Opportunity Exploitation#Impact Analysis#Risk Response Strategy
Full PMI-RMP Practice