nerdexam
PMIPMI

PMI-RMP · Question #359

PMI-RMP Question #359: Real Exam Question with Answer & Explanation

The correct answer is A: Risk monitoring and control process. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

The risk register is developed during the initial phases of a virtualized desktop deployment. The register is reviewed by peers, responses are planned, reviewed again, and risks are prioritized. After project completion, the risk register is reviewed as part of the formal lessons learned process. During the review, itis realized that the risk register was not updated, and many responses were not executed during the deployment. Which of the following options should have been performed during the execution of the project?

Options

  • ARisk monitoring and control process
  • BRisk management process
  • CRisk identification
  • DResponse planning

Topics

#Risk monitoring#Risk control#Risk register updates#Risk response execution

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions