nerdexam
PMIPMI

PMI-RMP · Question #360

PMI-RMP Question #360: Real Exam Question with Answer & Explanation

The correct answer is B: Improve the risk analysis to better define root causes.. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

A well established project begins to experience cost overruns and falls behind schedule. The project risk register identifies many risks and risk response plans in place, yet many risks are transitioning into issues. As the risks occur and become issues, many of the response plans are in progress, but not complete. The data from this graph represents the status of the project risks. Based on this information, what improvement to the risk management process is required?

Options

  • AIncrease the project risk identification and analysis.
  • BImprove the risk analysis to better define root causes.
  • CTransition to an issue management program and close the remaining open risks.
  • DReview remaining risk response plans and invest in schedule quality improvements.

Topics

#Risk analysis#Root cause analysis#Risk response effectiveness#Risk management process improvement

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions