nerdexam
PMIPMI

PMI-RMP · Question #361

PMI-RMP Question #361: Real Exam Question with Answer & Explanation

The correct answer is C: Change control board (CCB). See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Which of the following is an effective channel for risk mitigation assistance, project risk visibility and risk escalation support?

Options

  • AProject steering committee
  • BProject management office (PMO)
  • CChange control board (CCB)
  • DBoard of directors

Topics

#Risk Governance#Change Control#Risk Escalation#Risk Mitigation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions