PMIPMI
PMI-RMP · Question #361
PMI-RMP Question #361: Real Exam Question with Answer & Explanation
The correct answer is C: Change control board (CCB). See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
Which of the following is an effective channel for risk mitigation assistance, project risk visibility and risk escalation support?
Options
- AProject steering committee
- BProject management office (PMO)
- CChange control board (CCB)
- DBoard of directors
Topics
#Risk Governance#Change Control#Risk Escalation#Risk Mitigation
Community Discussion
No community discussion yet for this question.