nerdexam
PMIPMI

PMI-RMP · Question #362

PMI-RMP Question #362: Real Exam Question with Answer & Explanation

The correct answer is D: Conduct a low priority risk response planning workshop with key stakeholders.. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

The team has just completed a risk response planning session and identified responses for all the high and medium priority risks. What should the team do with the remaining low priority risks?

Options

  • ACreate risk responses later, as time allows.
  • BAdd the risks to a watchlist for periodic monitoring.
  • CRemove the risks from the risk register.
  • DConduct a low priority risk response planning workshop with key stakeholders.

Topics

#Risk Response Planning#Low Priority Risks#Stakeholder Engagement#Risk Prioritization

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions