PMIPMI
PMI-RMP · Question #362
PMI-RMP Question #362: Real Exam Question with Answer & Explanation
The correct answer is D: Conduct a low priority risk response planning workshop with key stakeholders.. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
The team has just completed a risk response planning session and identified responses for all the high and medium priority risks. What should the team do with the remaining low priority risks?
Options
- ACreate risk responses later, as time allows.
- BAdd the risks to a watchlist for periodic monitoring.
- CRemove the risks from the risk register.
- DConduct a low priority risk response planning workshop with key stakeholders.
Topics
#Risk Response Planning#Low Priority Risks#Stakeholder Engagement#Risk Prioritization
Community Discussion
No community discussion yet for this question.