PMIPMI
PMI-RMP · Question #391
PMI-RMP Question #391: Real Exam Question with Answer & Explanation
The correct answer is C: Close the risk during the next risk board meeting and keep it in the risk register.. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
A risk is identified early in the project. After six months, itis determined that the risk does not apply to this particular project. How should the risk be handled by the risk manager?
Options
- AIgnore the risk and concentrate only on the pertinent risks.
- BRemove the risk from the risk register and inform the project manager that it is no longer valid.
- CClose the risk during the next risk board meeting and keep it in the risk register.
- DConduct a risk analysis to determine how an inappropriate risk was formally accepted.
Topics
#Risk closure#Risk register management#Risk monitoring#Formal risk process
Community Discussion
No community discussion yet for this question.