nerdexam
PMIPMI

PMI-RMP · Question #390

PMI-RMP Question #390: Real Exam Question with Answer & Explanation

The correct answer is A: Technical performance. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

A risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex, but has rigorous implementation timelines, and very little cost reserve available to address potential problems. The project manager indicates that completing the project on time is critical, but should not be done at the expense of performance. Which aspect of risk impact is most important when designing the risk impact scale?

Options

  • ATechnical performance
  • BCost
  • CTechnical requirements
  • DSchedule

Topics

#Risk Impact Scale#Project Performance#Risk Prioritization#Risk Planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions