PMIPMI
PMI-RMP · Question #390
PMI-RMP Question #390: Real Exam Question with Answer & Explanation
The correct answer is A: Technical performance. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
A risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex, but has rigorous implementation timelines, and very little cost reserve available to address potential problems. The project manager indicates that completing the project on time is critical, but should not be done at the expense of performance. Which aspect of risk impact is most important when designing the risk impact scale?
Options
- ATechnical performance
- BCost
- CTechnical requirements
- DSchedule
Topics
#Risk Impact Scale#Project Performance#Risk Prioritization#Risk Planning
Community Discussion
No community discussion yet for this question.